We are getting there! 

Focus is on the east side of Queen St from Smith St to Mill St:
•Pierazcenzi is working on the Cenotaph and crosswalk at Queen and Canal.
•Pierascenzi has started to install subdrain from Smith St to the former railway. 
•Pierascenzi is removing conc curb and gutter and concrete sidewalk panels from Smith St to the former railway.

Bell is done the work on the west side of Queen St so that side can be done after the east side is completed. The west side will be done in the same fashion as the east side.

Fields Electric schedule for lighting downtown:
•All of the new decorative poles are now installed.
•They will be installing arms and fixtures today and tomorrow and installing conduit and wiring behind Pierascenzi as needed.
•The sectional steel pole at the Railway crossing has also been removed.

Remember that the possibility of inclement weather can affect their schedules.